Create a project

A project is the unit in which My Schedule shares a plan: it holds the uploaded planning data, the views that display it, and the users allowed to see it. Sign in to My Schedule with the administrator account to set one up.

Add a project​

Projects are added from Project management. Press [Project management] to open it.

The project management screen

Press [+ Add project]. Fill in the project's details in the window that appears, and choose the plan to apply to it under Plan.

Choosing a plan for the new project

info

The plan you choose here decides what the project can do — how long an upload period it accepts, how many styles it can show, and whether results can be entered. See Plans and project limits.

Press [Create]. The pop-up closes and the project you created appears in the list.

The newly added project in the list

Set the project up​

Click the name of the project you created to open it.

A project you have just created reports that no views have been configured for it. Press [Project detail settings] to configure its contents.

A project with no views configured yet

Project detail settings are grouped into sections:

SectionWhat it does
General infoReview and edit the project's name, description and plan.
ViewsChoose the views the project shares.
UsersChoose the users the project is shared with, and their permissions.
Auto ImportImport results into the project automatically — see Auto import.
Results data, and capacity adjustments dataWhich result properties users may enter, and how the Start and Finish buttons behave — see Results.

The rest of this guide follows an example that adds the Resource Gantt Chart under Views. Check that the view you want to share is ticked, then press [Save].

info

Which views you can choose depends on the project's plan and on your license. For what each one shows, see the view documentation.

Selecting the views to share

Press [Back] at the top left of the window to return to the previous screen, then click the icon of the view you added.

info

A message saying the required file could not be found means no planning data has been uploaded yet. That is the next step.

Now connect Asprova to this project and upload a plan: Connect Asprova.